What the Party Wall Act covers
Three kinds of work bring the Act in.
- Work to an existing party wall: cutting in a steel beam, removing a chimney breast attached to the shared wall, raising or thickening it, or underpinning it.
- Building a new wall on or up to the boundary line between the two properties.
- Digging within 3m of next door’s building and deeper than its foundations, or within 6m where the dig would cut a 45-degree line down from their foundations.
Which notice, and how much warning
Each kind of work has its own notice, served in writing on every owner of the neighbouring property, including a freeholder if the flat next door is leasehold.
What your neighbour can do
They can consent in writing, and the work goes ahead once the notice period ends. They can dissent. Or they can say nothing, and if they haven’t replied within 14 days, the Act treats that as a dispute.
A dispute isn’t a row. It means surveyors get appointed: either one agreed surveyor acting for both sides, or one each, who pick a third surveyor in case they can’t agree. The surveyors produce a party wall award setting out what will be done, how, and when workers can get in.
What a schedule of condition is for
Before work starts, the surveyor records the condition of the neighbour’s side: photos and notes of existing cracks, stains and loose plaster. If a new crack appears later, everyone can see whether it was there before. It protects you as much as them.
Who pays
The building owner, meaning whoever is doing the work, normally pays the reasonable fees of both surveyors. That’s worth building into the budget from the start, along with time, because an award can’t be rushed.
Jobs that don’t usually need a notice
Minor work to a party wall generally sits outside the Act: putting up shelves or kitchen units, replastering, or shallow chases for sockets and cables. Deeper cutting, anything structural, or anything that could weaken the wall is a different matter. If in doubt, a party wall surveyor can tell you quickly.
Getting the timing right
Serve the notice as early as you can, ideally once the drawings are settled and before you agree a start date. A notice lapses if the work hasn’t started within a year, so don’t serve it too early either.
Talking to next door before the paper arrives helps. A neighbour who hears about the steel over the fence is more likely to consent than one who finds a formal notice on the mat. For the structural side of knocking through a party wall, see knocking through walls.